Programming/Concept Plan
Residence Hall Programming/Concept Plan
The Residence Hall planning committee is nearing completion of the Programming/Concept Plan (Phase I) work with architects AndersonMasonDale.
The three visuals include:
1) a site concept drawing showing the overall building layout;
2) view of the standard double-bed unit; and 3) possible modular layouts for the kitchen/lounges, laundry room, and handicapped room.
The committee welcomes your comments to Joanna Anderson, Vice President for Student Services. |
 |
Project Goals
- Build residence hall complex to house 450-500 students
- Utilize modular design and construction for cost savings
- Provide an improved student living/learning environment
- “Wow” factor; gender integration; bed/bath combinations; community/learning spaces
- Provide new housing at an affordable cost
|
 |
Planning Committee
Residence Hall Planning Committee
- Casper College
- Joanna Anderson,
- Lynnde Colling,
- Lance Jones,
- Bill Landen,
- Barb Meryhew,
- Garth Shanklin,
- Mike Sawyer,
- Randy Stutheit
- AndersonMasonDale Architects
- Andy Nielsen, principal in charge;
- David Houston, project manager
- Amundsen Associates
- Jerry Amundsen, principal in charge;
- Ron Shosh, project architect
|
Notes/Comments
PHASE I - Programming & Conceptual Design (AndersonMasonDale Architects and Amundsen Associates)
- Established program components
- Student living spaces
- Double bedroom with bath
- Handicapped accessible double bedroom & bath
- Public Spaces
- Lobby, front desk, mail room, office, public restroom, vending, computer room, game room/ lounge, classroom/meeting room with warming kitchen
- Support Spaces
- Furniture/materials storage, HVAC systems, custodial storage
|
PHASE II – Schematic Design
- AndersonMasonDale will develop schematic design in conjunction with Project Management firm
- Establish cost estimates for project
- Finalize financing plan
- Revenue bonds, Foundation/other funds, Student costs
PHASE III – Design Development & Construction Documents
- Contractor Procurement (Negotiated GMP)
PHASE IV – Construction
PHASE V – Move-in & Celebration! |
 |
|
|
 |